Consumer Electronics

Domestic Alternative for Main-Control MCU

Cost down 18%, lead time cut by 3 weeks

The customer's imported MCU kept rising in price with longer lead times. Hangtong recommended a PIN-to-PIN compatible domestic part, with software regression verified within one week.

-18% Procurement cost
-3 wks Lead time
Detalles
Industrial Control

Global Sourcing for an EOL Interface IC

Line recovered, million-level stoppage avoided

A factory announced EOL for an interface IC the customer had used for 8 years. Hangtong sourced traceable stock globally while providing a long-term alternative — dual-track security.

72h Stock located
100% Traceable source
Detalles
Smart Hardware

One-Stop BOM Management for 200+ Parts

Procurement cycle down from 5 days to 1

Multi-category, small-batch, multi-lot orders consolidated to a single supplier — unified lead times and invoicing, with significantly lower procurement overhead.

200+ Categories consolidated
-80% Procurement time
Detalles
CASE 01 / Consumer Electronics

Domestic Alternative for Main-Control MCU

Cost down 18%, lead time cut by 3 weeks

Resultados clave Cost down 18%, lead time cut by 3 weeks

El desafío

The main-control MCU factory raised prices for two consecutive quarters, and lead times stretched from 12 to 26 weeks. Peak season meant no stock-outs — and no time for a redesign.

Nuestra solución

We compared packages, clock speeds, peripherals, Flash/RAM and temperature ranges across 6 candidates, shortlisted 2 PIN-to-PIN compatible parts, and provided free samples — software regression and peripheral testing done within a week.

Marcas implicadas ST GigaDevice Microchip
CASE 02 / Industrial Control

Global Sourcing for an EOL Interface IC

Line recovered, million-level stoppage avoided

Resultados clave Line recovered, million-level stoppage avoided

El desafío

The EOL announcement left the customer with open orders still in delivery. Redesign cost and schedule were both unacceptable.

Nuestra solución

Activated global distribution channels, located two traceable stock lots within 72 hours with inspection records archived; provided a long-term alternative with a validation checklist for the next hardware revision.

Marcas implicadas TI ADI onsemi
CASE 03 / Smart Hardware

One-Stop BOM Management for 200+ Parts

Procurement cycle down from 5 days to 1

Resultados clave Procurement cycle down from 5 days to 1

El desafío

Each unit carried 200+ part numbers spread across 9 suppliers. Every batch meant repeated quoting, comparison, chasing and reconciliation — procurement was drowning in trivia.

Nuestra solución

One quote for the full BOM, consolidated supply and unified lead times; buffer plans for long-lead parts and cost-down alternatives where substitutable — procurement talks to one dedicated helper only.

Marcas implicadas Samsung Micron Espressif JST